Repeat orders now provide about 70% of 3T-AM’s revenue, while product development still occupies most of its team’s time.

3T-AM shifts metal additive manufacturing toward repeat production

Repeat orders now account for around 70% of 3T-AM’s revenue, but developing new products still takes roughly 80% of the Newbury manufacturer’s team time. That split captures the challenge facing metal additive manufacturing suppliers: they need reliable, repeatable production while continuing to qualify products and processes that may take years to generate steady demand.

3T Additive Manufacturing at work. Photo via 3T-AM.

Eddie Andrews joined 3T-AM as commercial director in November 2021, when the business could produce one-off metal components for hundreds of customers. The harder task was making the same part again at an agreed cost and on schedule. He describes the shift as making additive manufacturing “boring”: a routine production process with predictable handoffs and delivery.

The change shows up in how the company buys equipment. In the past, 3T-AM might acquire an EOS M400 to explore a material and see whether demand followed. Now, Andrews says, customer programmes account for the capacity of incoming machines before they arrive. That makes an investment easier to justify, though a busy order book can leave little machine time for trials and new product work.

Building repeatable production

3T-AM traces its origins to 1997, and its first metal machine arrived around 2008. Years of taking on individual prototype jobs had created a long list of processes. After the 2021 reset, the company narrowed its customer base, gave larger accounts more influence over development priorities and simplified accumulated procedures. Much of the work was still manual as the team worked out which operations it could repeat reliably.

Responsibility for each job also changed. When a printing engineer first reviewed a drawing, the initial question tended to be how to print it. That early decision could shape the work passed to subsequent operations. Now, a product owner is accountable for delivering the finished component, while printing and machining specialists agree on the part’s required condition at each handoff.

Andrews argues that an additive manufacturer needs strong CNC machining capability. Bringing machining in-house gave 3T-AM more control over cost, quality and delivery dates. Larger multi-laser printers increased productivity at the printing stage, but capacity alone can’t establish when a finished part will reach a customer. The whole production route has to be managed.

3T-AM. Photo via 3T-AM.
3T-AM. Photo via 3T-AM.

Demand for production orders has risen and then eased, making the balance between development work and repeat orders difficult to manage. Turning away too much prototype work during a busy period could leave spare capacity when orders fall. Repeat business gives the company more room to choose development projects, but some will never become production contracts. Andrews says the company still needs to take part in the development process to discover which ones will.

Capacity tied to demand

Austrian precision manufacturing group SBO acquired 3T-AM in October 2025. The Newbury business recorded around £5 million in sales in 2024. SBO brought experience machining downhole drilling equipment, including components up to ten metres long, while 3T-AM offered metal printing expertise and access to a different group of industrial customers. SBO’s account of the acquisition describes the addition to its precision technology division.

SBO approved a five-year business plan for 3T-AM. Andrews recalls being asked whether the company could reach its goals faster. In August 2026, the group reported that 3T-AM had added an EOS M400 in the second quarter, ordered another printer and invested in post-processing. These purchases were part of a seven-printer expansion across its UK and US operations. The capacity update gives details of the expansion.

Andrews sees two distinct reasons to invest: contracted customer demand and capabilities the company does not yet offer. A full order book supports new production equipment, but can restrict the time available to qualify another material or develop a new part. He recalls a pre-pandemic aerospace enquiry for which one family of components would have required 16 multi-laser systems to cover only part of the demand. The example illustrates the space, capital and capacity that a large production commitment can require, and why some manufacturers keep substantial additive work in-house.

Making the economics visible

For some customers, replacing a casting with a printed part can make sense because it shortens lead time, even when the unit cost is similar. Higher volumes make the calculation harder. Maintenance contracts and consumables contribute to machine costs, while single-shift operation leaves fewer productive hours over which to spread them. Andrews sees room to learn from CNC shops that run around the clock. Support removal is one potential area for more automation, since the process can still rely on an experienced operator’s knowledge of a particular job.

A project with Honeywell Aerospace will test the case for replacing a conventionally made component with an additively manufactured version. Funded by the Aerospace Technology Institute, the work includes a 12-month life-cycle assessment by the NCC’s sustainability team in Bristol. The assessment covers manufacture, service and end of life. Printing closer to the component’s final shape could use less feedstock and leave less metal to machine away than starting from billet; the study will compare both manufacturing routes and consider any in-service benefit from the redesigned component.

3T-AM is also connecting its factory and enterprise systems as it develops digital product passports. Andrews wants each component’s manufacturing carbon information to accompany it at no extra charge by the end of 2028. For purchasing teams compiling supply-chain emissions reports, that would make production data part of a routine order. The practical test for 3T-AM’s next phase will be whether it can deliver that information alongside parts at the same predictable cost, quality and pace it is working to establish.

Source: Michael Petch · 3dprintingindustry.com