BAM Starts Two-Phase Construction of 750-Pupil Presentation De La Salle College
- Sarah
- 535 reads
The Bagenalstown project includes a new school, sports hall and dedicated SEN accommodation, with construction planned around the existing school’s continued operation.

Building a new school while the existing one remains in use makes construction sequencing central to the project. BAM has begun work on a new 750-pupil facility for Presentation De La Salle College in Bagenalstown, County Carlow, with construction planned in two phases to limit disruption to pupils and staff.

The development will add a new school building, a sports hall and dedicated accommodation for pupils with special educational needs (SEN). The stated aim is to provide purpose-built spaces for teaching, learning, recreation and student wellbeing, including settings where pupils with additional needs can learn alongside their peers.
Phased work around an operating school
Keeping the current school operational throughout construction shapes how the work must be delivered. The two-phase approach is intended to manage the interface between building activity and the day-to-day life of the school. The project description does not set out the phase boundaries or construction timetable, so the precise sequence of work has not been specified.
That arrangement puts practical demands on planning: construction and school activities will need to coexist over the build period, while access to existing facilities continues. The project’s stated focus on minimising disruption reflects that constraint. The new facilities are intended to serve the school once construction is complete, but no completion date or detailed specification for the building has been given.
The planned mix of general school space, a sports hall and dedicated SEN accommodation is significant because it brings learning and recreation facilities into one development. The SEN provision is described as supporting inclusion alongside peers. No room layouts, equipment schedules or accessibility specifications have been provided, so the exact design response to different learning needs remains unspecified.
Part of a three-school programme
Presentation De La Salle College is one of three school developments in Project Boyne Lot 2, covering counties Carlow, Kildare and Meath. BAM is the main contractor for the bundle.
The Bagenalstown project therefore sits within a broader regional programme, while its construction plan has to respond to the operating conditions at this particular school. The other developments are identified as part of the same bundle, but the available project details do not describe their designs, schedules or construction arrangements.
The start of construction was marked by a sod-turning ceremony attended by Jennifer Murnane O’Connor, identified as Minister of State at the Department of Health and TD for Carlow-Kilkenny. The event marked the beginning of work on a facility intended to serve 750 pupils.
Design intent and delivery experience
Darren Devane, BAM Ireland’s Director of Building, said the design is intended to support different learning needs, encourage inclusion and give pupils the opportunity to thrive. He also described delivery alongside continuing education as a task requiring careful planning and close collaboration.
Principal Michael Hickey said the development would provide a new facility in which students’ talents could be nurtured, ambitions encouraged and friendships strengthened. His remarks place the building in the context of the school community’s longer-term needs, as well as its immediate teaching and recreation requirements.
BAM has also pointed to its work on other education facilities in Ireland. Its examples include the recently completed Greystones Community College in County Wicklow, which provides places for 1,000 pupils, and new primary and secondary school developments at Sandymount and Citywest in Dublin. Those projects offer context for the contractor’s education-sector experience; the information provided does not establish whether their designs or delivery methods will be used at Bagenalstown.
For Presentation De La Salle College, the next practical measure of progress will be how the phased build accommodates a school that continues to operate on site. The development’s intended capacity, sports hall and dedicated SEN spaces define its scope; details such as the construction schedule, building specification and completion date have yet to be stated.